b'NTCA FIVE-STAR MEMBER SPOTLIGHTAllstate projectsAt the Hobby Doubletree, the work Allstate did has stood the test of time. There was a lot of detail to be worked out on the three fountains that incorpo-rated mosaics, thick stone and stack stone. Specific details were needed for waterproofing, level waterfall edge work etc. Allstate also did the granite tops on this project. The Klein Cain High School project was an over $2,000,000 tile project and included more than 120,000 sf. of tile. Allstate used a combination of in-house employees and subcontractors to get the job done. The proj-ect manager, Cecil Zachary of Satterfield & Pontikes, had not worked with Allstate before. Now, because of his experi-ence with Tommy Vus atten-tion to detail, Allstate has done four more projects in the last two years with Satterfield & Pontikes.70TileLetter | September 2019'